Myagdi, November 16
Water supply from the Dandakharka source has resumed in Beni Bazar, the district headquarters of Myagdi, after one and a half months. The Beni Drinking Water and Sanitation Consumers’ Institution has started supplying water to the market through a temporary pipeline connected to the sources at Rithakharka and Dandakharka in Annapurna Rural Municipality-8.
The institution’s Chairperson, Ramesh Giri, said water supply resumed on November 13 after repairs to the 14-kilometre main pipeline.
“After one and a half months of effort, we have started supplying water at a rate of eight litres per second,” he said. “Temporary and alternative pipelines have been constructed along the Rahupare-Galeshwar and Dallepipal-Beni sections.”
Giri said the pipeline route had to be changed after landslides began occurring on the slopes of Khoriya and Khareini in Beni. As a result, around three kilometres of new pipeline had to be laid through the Dallepipal-Kalipul-Beni Ring Road-Darwang Bus Park area.
Following the disaster, water was collected from the Kopre source at three litres per second, the alternative Amreni source at 3.4 litres per second, and Rahuwada at four litres per second. It was then distributed to consumers on a rotational basis. However, the Amreni and ward-level alternative sources have since dried up. As these alternative sources are no longer available, the pipeline was repaired to resume supply from the Rithakharka and Dandakharka sources.
According to the institution’s Vice-chairperson, Rajendra Shrestha, Beni Bazaar requires more than 20 litres of water per second. The institution supplies drinking water to around 25,000 people living in 1,200 households across wards 2, 7 and 8 of Beni Municipality.
Shrestha said water was being distributed by dividing neighbourhoods into groups and following a rotational schedule because the institution could not meet demand.
The pipeline bringing water from the Dandakharka and Rithakharka sources, which together have a supply capacity of 22 to 25 litres per second, had remained out of operation following the disaster. With no other immediate alternatives available, a temporary pipeline was laid along the Beni-Jomsom road.
The institution’s Secretary, Keshav Prasad Regmi, said an alternative pipeline had been constructed around the outskirts of the market after landslides in Khoriya, Khareini and Barahapakho threatened the pipeline section between Kalipul in Beni and the water collection centre at Barahapakho.
According to Regmi, a cost estimate of Rs 147 million for an immediate project and Rs 700 million for a long-term project has been prepared to improve drinking water supply in Beni. A proposal has been submitted to the Department of Water Supply and Sewerage Management.
—RSS