Kathmandu, November 25
It will take another three days to remove the unstable section of the slope at Ghoptebhir along the Muglin–Naubise section of the Prithvi Highway, with traffic being halted daily to facilitate the work.
Sachendra Mishra, information officer at the Nagdhunga–Muglin Road Project’s western section, said the work has been taking longer due to the difficult terrain and challenging working conditions.
“Vehicles have been stopped for five hours daily since Saturday afternoon to remove the dangerous section. If no further complications arise, we aim to complete the work within the next three days,” Mishra said.
Excavators are being used to cut down the unstable section of the slope from above, while workers clear debris from the road below. Traffic is being halted daily from 11 am to 4 pm to allow the work to proceed.
According to Ishwar Nepal, an engineer at the construction company, an excavator has been positioned on the hillside nearly 100 metres above the road to cut away the unstable section.
“Progress has been slow because the work is extremely risky,” he said.
An excavator was buried by a landslide on Tuesday after a section of the slope collapsed. The machine was subsequently cleared and work resumed, Nepal said.
The construction team is also preparing to deploy another excavator on the hillside if possible.
Meanwhile, road widening work has also begun at Dahaki Khola, between Chumlingtar and Kurintar, while traffic remains halted. A 100-metre stretch at the location needs to be widened by two metres. Excavators and a loader are being used to cut into the hillside at the site.