Kathmandu, November 24
Rastriya Swatantra Party (RSP) lawmaker Manish Jha has warned that Madhesh could erupt in protests if the Sunkoshi-Marin Diversion Project is scrapped, urging the government and concerned agencies to present a clear plan and timeline for resuming the long-delayed project.
Speaking at a meeting of the Public Accounts Committee on Tuesday, Jha said, “If it is cancelled, there will be no option left other than Madhesh taking to the streets.”
Jha described the Sunkoshi-Marin Diversion Project as a crucial initiative for Madhesh, saying its suspension had disappointed farmers and residents of the province. He called on the concerned agencies to clarify why work had been halted, what plans they had for the project and how it would move forward.
The project, launched around six years ago, was designed to provide irrigation to approximately 180,000 bighas of land across parts of Bara, Rautahat, Sarlahi, Mahottari and Dhanusha districts. Its contract has now been cancelled.
The project was also expected to generate 28 megawatts of electricity and was being developed as a national pride multipurpose project, Jha said.
He questioned why work had not progressed even after the breakthrough of the project’s 13.3-kilometre tunnel on April 26, 2024.
“More than two years have passed since the breakthrough, but the work has not progressed. It would be good to have clarity on three things — why the work has not progressed, what the situation is regarding its closure, and what the way forward is,” he said.
Jha said agriculture remains the primary economic source for Madhesh and that uncertainty surrounding irrigation projects could affect agricultural production and the province’s future.
“Madhesh has no mountains to show off, nor does it have hydropower to produce. Agriculture is what we have, and even that is being left entangled in such complications,” he said.
He said residents expected the Sunkoshi-Marin Diversion Project to help address increasing desertification in Madhesh and improve water availability, urging authorities not to delay its implementation unnecessarily.
Jha said lawmakers could raise the issue in Parliament and other forums and exert pressure to move the project forward if the concerned agencies presented a clear plan. He demanded further information and a concrete way forward.
A complaint has been filed with the Public Accounts Committee of the House of Representatives alleging that the cancellation of the contract for civil, hydromechanical and related infrastructure works was procedurally flawed, despite the completion of tendering procedures.
The committee began discussions on the issue after receiving the complaint. Director General of the Department of Water Resources and Irrigation Dinesh Rajouria and other officials attended the meeting.
Rajouria, however, has maintained that the decision to cancel the tender process was legally valid.