Kathmandu, July 17
A parapet construction and floodlight installation works are currently underway at the Tribhuvan University International Cricket Ground, Kritipur.
The work, which began in March and was originally scheduled to be completed by May, has not been completed even within the extended deadline of the end of mid-July.

Now, the construction company is continuing the work paying daily penalties and has committed to completing it within a month.
So far, 4,000 seats have been installed, and 3 out of the 6 floodlight poles have been erected.