Kathmandu, November 29
The government has authorised the Ministry of Finance to extend the Millennium Challenge Corporation (MCC) compact by one year.
Ministry sources said a Cabinet meeting authorised the ministry to extend the completion deadline for MCC compact projects by up to a year, provided costs do not rise.
Projects funded by MCC grants must be completed within five years. However, Nepal and the US have both agreed that a one-year extension is warranted, sources said. The work was suspended for several months after the project entered into force, as the US reviewed its aid. Natural disasters also caused delays.
The MCC project in Nepal came into effect on August 30, 2023. The compact states that the project must be completed within five years of that date, or the US grant will be returned.
In the meantime, implementation was halted for some time to review the assistance after Donald Trump was elected US president. Ministry sources said the severe floods in the Trishuli River last year and this year also affected the project. In view of these factors, preparations are underway to extend the implementation period by up to a year.
During Finance Minister Dr Swarnim Wagle’s visit to the US, MCC’s acting vice president Jason Small met him. The ministry sources said the two sides discussed ensuring successful implementation, even if that meant extending the deadline.
MCA-Nepal had sent a proposal to the Finance Ministry seeking a decision on the extension. Based on that proposal, the ministry took the matter to the Cabinet.
Nepal will now send its extension request to the MCC board. The sources said the board, which meets in December, is likely to decide whether to grant its consent.
The Government of Nepal and MCC signed the compact on September 14, 2017 to build transmission lines, substations and road infrastructure. At the time, MCC had agreed to provide Nepal with a $500 million grant.
However, prolonged political disputes over implementing the agreement meant it took Nepal’s Parliament more than four and a half years to ratify the compact. Parliament ratified it only on February 27, 2022, with an interpretative declaration. The project came into force on Bhadra 13, 2080, six years after the agreement was signed.
The US initially agreed to provide a $500 million grant for the project and later added $50 million. Its total grant now stands at $550 million.
Nepal had initially agreed to contribute $130 million. As project costs rose, Nepal committed in May 2023 to invest an additional $67 million.
The project is therefore being implemented with $747 million, made up of $550 million from the US government and $197 million from the Government of Nepal. It covers transmission lines, substations and road improvements.
Of the projects funded by MCC grants, an 18-km transmission line has recently been completed. Contracts have also been awarded for 297 km of transmission lines and three substations. A contract has also been awarded to upgrade the road from Dhanakhet to Lamahi in Dang, along the East–West Highway.
MCA-Nepal completed the 18-km transmission line, from the New Butwal substation to the Indian border, within nine months of laying its foundation stone. The work was finished on September 13.
The MCC project is building substations at Damauli in Tanahun and Ratmate in Nuwakot, as well as a 400 kV substation in Nawalparasi.
Earlier, a tender was invited three years ago to build a total of 315 km of transmission lines. All bidding processes were cancelled on October 13, 2023, after the lowest bid came in 60 percent above the estimated cost.
When the transmission line project was re-evaluated, the earlier budget proved insufficient. The US Congress then added a $50 million grant, equivalent to about Rs 7 billion.
The 18 km up to the border was then tendered separately. For the remaining 297 km, construction agreements were signed in three packages.
These contracts were awarded on the second attempt, after the first round was cancelled. Their terms run beyond the compact’s term, so the compact must be extended for these projects to be completed.
On January 20, 2025, US President Trump began a review of foreign aid and halted implementation of the agreement with Nepal. In the last week of July 2025, the US government recommended continuing the MCC project in Nepal.
The project was thus suspended for about seven months. Last year’s Trishuli flood also disrupted implementation, and this year’s flood has added further delays.
In March, while the US was still reassessing its foreign aid, MCC wrote to Nepal, permitting some critical procurement and office-operation work.