Kathmandu, November 22
A parliamentary committee has shown interest in the Sunkoshi Marin Diversion Multipurpose Project following a complaint filed with the Public Accounts Committee under the House of Representatives.
The complaint alleges that the contract invited for the construction of civil, hydromechanical and related structures was cancelled at the final stage despite all tendering procedures having been completed. It claims that the cancellation was procedurally flawed.
The complainant has argued that proceeding with the cancellation of the contract would cause financial losses to the state.
Following the receipt of the complaint, the committee has decided to hold discussions on the matter. A committee meeting has been scheduled for Tuesday morning, November 24.
The agenda for the meeting, called for 9:30 am on Tuesday, includes a discussion on the Sunkoshi Marin Diversion Multipurpose Project.
The committee will also discuss a complaint received regarding the expansion of the Nepal Electricity Authority’s digital communication network and Supervisory Control and Data Acquisition (SCADA) system.
Committee Chairperson Bharat Bahadur Khadka confirmed that the committee would discuss the complaints it had received.
“We will study the complaints, examine the facts and hold discussions with the concerned stakeholders. We will proceed based on the facts,” Khadka told Onlinekhabar.
The project had invited bids for the construction of civil, hydromechanical and related structures through a notice published on June 8.
However, the project said the contract was cancelled in the second week of Kartik in accordance with Section 3(2) of the Public Procurement Act, 2007.
In a notice issued by the project director regarding the cancellation, the project apologised to the bidders for the inconvenience caused by the decision.
The parliamentary committee has taken an interest in the matter after receiving a complaint alleging that the contract was cancelled when the process for awarding a new contract for the Sunkoshi Marin Diversion Multipurpose Project had reached its final stage.