Electricity production disrupted as Trishuli power house catches fire

File image: A hydropower project location

Betrawati, January 3

Power generation from Trishuli Hydropower Centre in Nuwakot district has disrupted following a fire in the power house on Wednesday evening.

With the fire, a total of 53 megawatt including 21 megawatt from Trishuli Hydropower Project and 14 megawatt from Devighat Hydropower Project has been disconnected from the national transmission line.

Chief of Trishuli Hydropower Project, Tara Dutta Bhatta, said that a generator of 6.6 KV of Breaker No. 6 was completely destroyed in the fire that happened following the excessive heat generation in the electricity transmitter.

Bhatta added that around 10 million rupees would be required to repair the damaged equipment while around a week was expected to take to resume the power transmission from the Centre.

Earlier, fires had occurred on July 10 and November 24, 2018 in the power house.